6.10 Hardware Refresh Strategy
| Item |
Details |
| Organization |
Abhavtech.com |
| Version |
2.0 |
| Last Updated |
December 2025 |
1. Hardware Lifecycle Overview
1.1 Current Inventory EoL Status
| Hardware Category |
Model |
Qty |
EoS Date |
EoL Date |
Status |
| Border Nodes |
C9500-48Y4C |
12 |
TBD |
TBD |
✅ Current |
| Control Plane |
C9500-24Y4C |
12 |
TBD |
TBD |
✅ Current |
| Edge (mGig) |
C9300-48UXM |
200 |
TBD |
TBD |
✅ Current |
| Edge (Standard) |
C9300-48U |
100 |
TBD |
TBD |
✅ Current |
| WLC |
C9800-40 |
10 |
Feb 2025 |
Feb 2030 |
⚠️ EoS Soon |
| WLC Large |
C9800-80 |
2 |
Feb 2025 |
Feb 2030 |
⚠️ EoS Soon |
| Wi-Fi 6 APs |
C9130AXI |
235 |
TBD |
TBD |
✅ Current |
| Wi-Fi 6E APs |
C9136I |
470 |
TBD |
TBD |
✅ Current |
| Wi-Fi 7 APs |
CW9176I |
235 |
TBD |
TBD |
✅ Current |
| ISE |
SNS-3755-K9 |
4 |
TBD |
TBD |
✅ Current |
| ISE PSN |
SNS-3715-K9 |
12 |
TBD |
TBD |
✅ Current |
| Catalyst Center |
DN2-HW-APL-XL |
6 |
TBD |
TBD |
✅ Current |
1.2 EoL Definitions
End of Sale (EoS): No longer available for purchase
End of Software Maintenance (EoSM): No new software releases
End of Vulnerability Support (EoVS): No security patches
End of Life (EoL): No support whatsoever
Timeline:
EoS ──► EoSM (typically +3 years) ──► EoVS (+1 year) ──► EoL (+1 year)
2. 5-Year Refresh Roadmap
2.1 Refresh Timeline
┌─────────────────────────────────────────────────────────────────────┐
│ 5-Year Hardware Refresh Roadmap │
├─────────────────────────────────────────────────────────────────────┤
│ │
│ Year 1 (2026): Initial Deployment │
│ ├── All new hardware deployed │
│ ├── SmartNet contracts active │
│ └── Baseline established │
│ │
│ Year 2 (2027): WLC Refresh │
│ ├── C9800-40/80 reaching EoS │
│ ├── Evaluate C9800-L or next-gen WLC │
│ ├── Budget: $X,XXX │
│ └── Timeline: Q2 2027 │
│ │
│ Year 3 (2028): Branch Optimization │
│ ├── Evaluate branch switch refresh needs │
│ ├── Consider Meraki for small branches (if applicable) │
│ ├── Wi-Fi 6 AP refresh to Wi-Fi 7 (oldest locations) │
│ ├── Budget: $X,XXX │
│ └── Timeline: Q3-Q4 2028 │
│ │
│ Year 4 (2029): AP Technology Refresh │
│ ├── Wi-Fi 6 APs (C9130) reach 4+ years │
│ ├── Replace with Wi-Fi 7/8 APs │
│ ├── Evaluate 6 GHz only deployments │
│ ├── Budget: $X,XXX │
│ └── Timeline: Q2-Q4 2029 │
│ │
│ Year 5 (2030): Major Platform Review │
│ ├── Full architecture review │
│ ├── Catalyst Center appliance refresh │
│ ├── ISE appliance capacity review │
│ ├── Switch platform evaluation │
│ ├── Budget: $X,XXX+ │
│ └── Timeline: Full year planning │
│ │
└─────────────────────────────────────────────────────────────────────┘
2.2 Annual Refresh Budget
| Year |
Category |
Budget |
Notes |
| Year 1 |
Initial CapEx |
$X,XXX |
Full deployment |
| Year 2 |
WLC Refresh |
$X,XXX |
12 WLC replacement |
| Year 3 |
Branch Optimization |
$X,XXX |
Selective upgrades |
| Year 4 |
AP Refresh |
$X,XXX |
235 APs (Wi-Fi 6→7) |
| Year 5 |
Major Platform |
$X,XXX |
Full review |
| 5-Year Total |
|
$X,XXX |
|
3. Component-Specific Refresh Plans
3.1 Wireless LAN Controller Refresh (Year 2)
WLC_Refresh_Plan:
Current_State:
Model: C9800-40 (10 units), C9800-80 (2 units)
EoS: February 2025
EoL: February 2030
Support: SmartNet until 2030
Risk_Assessment:
- EoS means no new purchases
- Still supported until 2030
- No new features after EoSM
- Security patches until EoVS
Recommendation:
Option_A: Refresh in Year 2 (2027)
- Replace with successor model
- Take advantage of new features
- Stay ahead of EoSM
Cost: ~$X,XXX
Option_B: Run until Year 4 (2029)
- Maximize investment
- Risk: No new features, fewer spare parts
- Must refresh before EoL (2030)
Cost: Deferred
Decision: Option A (Proactive refresh Year 2)
Migration_Plan:
Q1_2027:
- Evaluate successor models
- Lab testing
- Budget approval
Q2_2027:
- Purchase new WLCs
- Staging and configuration
Q3_2027:
- Rolling replacement (site by site)
- Old WLCs as spares
Q4_2027:
- Complete migration
- Decommission old WLCs
3.2 Access Point Refresh (Year 4)
AP_Refresh_Plan:
Current_State:
Wi-Fi 6 (C9130AXI): 235 APs - Deployed 2026
Wi-Fi 6E (C9136I): 470 APs - Deployed 2026
Wi-Fi 7 (CW9176I): 235 APs - Deployed 2026
Refresh_Strategy:
Year_4_Refresh (2029):
Target: Wi-Fi 6 APs (oldest technology)
Replace_With: Wi-Fi 7/8 APs (whatever is current)
Quantity: 235 APs
Budget: $X,XXX(~$X,XXX/AP with licenses)
Year_6_Refresh (2031):
Target: Wi-Fi 6E APs
Replace_With: Current technology
Quantity: 470 APs
Budget: ~$X,XXX(future estimate)
Technology_Considerations:
- Wi-Fi 7 (802.11be) widespread by 2029
- 6 GHz spectrum fully utilized
- Consider Wi-Fi 8 (802.11bn) if available
- MLO (Multi-Link Operation) standard
3.3 Catalyst Center Appliance Refresh (Year 5)
Catalyst_Center_Refresh:
Current_State:
Model: DN2-HW-APL-XL
Quantity: 6 (3 primary + 3 DR)
Deployment: 2026
Expected_Life: 5-7 years
Year_5_Review:
Evaluate:
- [ ] Performance metrics (CPU, memory, storage)
- [ ] Capacity vs. growth projections
- [ ] New appliance capabilities
- [ ] Cloud-managed options
Options:
Option_A: Hardware refresh
- New appliances
- On-premises continues
- Cost: ~$X,XXX
Option_B: Cloud migration
- Cisco managed cloud
- Reduced on-prem hardware
- Cost: OpEx model
Option_C: Extend existing
- If capacity sufficient
- Continue SmartNet
- Minimal cost
4. SmartNet and Support Planning
4.1 SmartNet Contract Summary
| Category |
Coverage |
Expiry |
Annual Cost |
Renewal Strategy |
| Switching |
24x7x4 |
2031 |
$X,XXX |
5-year prepaid |
| Wireless |
24x7xNBD |
2031 |
$X,XXX |
5-year prepaid |
| ISE/Catalyst Center |
24x7x4 |
2031 |
$X,XXX |
5-year prepaid |
| Total Annual |
|
|
$X,XXX |
|
4.2 Support Renewal Timeline
Support_Renewal_Schedule:
Year_3 (2028):
Action: Evaluate renewal options
Tasks:
- Review support utilization
- Assess hardware health
- Get renewal quotes
- Negotiate multi-year discount
Year_4 (2029):
Action: Execute renewal
Tasks:
- Renew SmartNet (3-5 year term)
- Update coverage levels if needed
- Align with refresh plans
- Budget for refresh items
Negotiation_Tips:
- Bundle with new purchases
- Multi-year commits (3-5 years)
- Volume discounts
- Include refreshed hardware
5. License Management
5.1 DNA License Renewal
DNA_License_Management:
Current_Licenses:
Term: 5-year subscription
Start: 2026
Expiry: 2031
Tier: DNA Advantage
Devices_Licensed:
Switches: 350 units
Wireless Controllers: 14 units
Access Points: 940 units
Year_5_Renewal (2031):
Action: Renew DNA licenses
Considerations:
- Device count may have grown
- New devices need licenses
- Evaluate Essentials vs. Advantage
- Consider perpetual vs. subscription
Budget_Planning:
Current_Annual_Equivalent: ~$X,XXX Growth_Factor: 10% per year
Year_5_Estimate: ~$X,XXX```
### 5.2 ISE License Planning
```yaml
ISE_License_Management:
Current_Licenses:
Base: 25,000 endpoints (perpetual)
Plus: 25,000 endpoints (perpetual)
Apex: 10,000 endpoints (perpetual)
Device Admin: 400 devices (perpetual)
Growth_Planning:
Current_Usage: 25,000 endpoints
Year_5_Projected: 37,000 endpoints
Gap: 12,000 endpoint licenses
License_True-Up_Schedule:
Year_2: Review usage, order if >90% utilized
Year_3: True-up purchase if needed
Year_5: Major review with refresh
Budget:
ISE_Base_per_endpoint: ~$X,XXX(list)
ISE_Plus_per_endpoint: ~$X,XXX(list)
Additional_12K_endpoints: ~$X,XXX```
---
## 6. Spare Parts Strategy
### 6.1 Recommended Spares Inventory
| Component | Model | Quantity | Location | Purpose |
|-----------|-------|----------|----------|---------|
| Edge Switch | C9300-48UXM | 4 | Mumbai (2), NJ (2) | Hot spare |
| Border Module | C9500-NM-8X | 2 | Mumbai, London | Uplink spare |
| Power Supply | PWR-C1-1100WAC | 6 | Regional | Switch PS spare |
| WLC | C9800-40 | 1 | Mumbai | HA spare |
| AP | C9136I | 20 | Regional (5 each) | Replacement |
| ISE | SNS-3715-K9 | 1 | NJ | PSN spare |
### 6.2 Spares Budget
| Year | Spares Investment | Notes |
|------|-------------------|-------|
| Year 1 | $X,XXX| Initial spares pool |
| Year 2 | $X,XXX| Replenishment |
| Year 3 | $X,XXX| Add WLC spares |
| Year 4 | $X,XXX| Replenishment |
| Year 5 | $X,XXX| Pre-refresh buffer |
| **Total** | **$X,XXX** | 5-year spares |
---
## 7. Technology Watch
### 7.1 Emerging Technologies to Monitor
| Technology | Timeline | Impact | Action |
|------------|----------|--------|--------|
| Wi-Fi 8 (802.11bn) | 2028-2030 | Next-gen wireless | Monitor standards |
| 400G Switching | 2026-2028 | Data center | Evaluate for DC |
| AI-Native Networking | Ongoing | Operations | Early adoption |
| Private 5G | 2027+ | IoT/OT coverage | Pilot potential |
| SASE Maturity | Ongoing | Remote access | Continued integration |
### 7.2 Annual Technology Review Checklist
```yaml
Annual_Tech_Review:
Q1_Activities:
- [ ] Review Cisco product roadmaps
- [ ] Attend Cisco Live sessions
- [ ] Evaluate new features in current products
- [ ] Assess competitor offerings
Q2_Activities:
- [ ] Lab test new features
- [ ] Pilot promising technologies
- [ ] Update 3-year roadmap
Q3_Activities:
- [ ] Budget planning for next year
- [ ] Refresh recommendations to leadership
- [ ] Training needs assessment
Q4_Activities:
- [ ] Finalize budget
- [ ] Initiate procurement for approved items
- [ ] Update documentation
8. Summary: 5-Year Financial Plan
| Year |
CapEx |
OpEx (Support) |
Total |
| Year 1 |
$X,XXX |
$X,XXX |
$X,XXX |
| Year 2 |
$X,XXX |
$X,XXX |
$X,XXX |
| Year 3 |
$X,XXX |
$X,XXX |
$X,XXX |
| Year 4 |
$X,XXX |
$X,XXX |
$X,XXX |
| Year 5 |
$X,XXX |
$X,XXX* |
$X,XXX |
| Total |
$X,XXX |
$X,XXX |
$X,XXX |
*Year 5 includes license renewals
Document Version: 2.0
Abhavtech.com - SD-Access Implementation