4.11 Rollback Procedures

4.11.1 Rollback Decision Matrix

Issue Severity Impact Rollback Trigger
>25% users cannot authenticate Critical Business impact Immediate rollback
Voice quality degraded High Communication impact Rollback if >15 min
Single floor issues Medium Limited impact Floor-level rollback
Minor issues, workaround available Low Minimal impact Continue, fix forward

4.11.2 Full Site Rollback Procedure

FULL ROLLBACK PROCEDURE - MUMBAI

Step 1: Declare Rollback (PM Decision)
        Time: T+0

Step 2: Notify Stakeholders
        Time: T+5 minutes
        - Send rollback notification
        - Update bridge call

Step 3: Disable Fabric on All Edge Nodes
        Time: T+10 minutes
        # From DNAC: Provision > Fabric Sites > Mumbai
        # Disable Host Onboarding (all floors)

Step 4: Restore Legacy Switch Configuration
        Time: T+20 minutes
        # For each edge switch:
        configure replace flash:pre-cutover-backup.txt

Step 5: Verify Legacy Operation
        Time: T+40 minutes
        show vlan brief
        show spanning-tree summary
        show mac address-table dynamic

Step 6: User Validation
        Time: T+50 minutes
        - Test user authentication
        - Test application access
        - Test voice quality

Step 7: Rollback Complete
        Time: T+60 minutes
        - Confirm all users operational
        - Schedule post-mortem
        - Plan remediation

4.11.3 Partial Rollback (Single Floor)

# Floor-level rollback if issues isolated to one floor

# Step 1: Identify affected floor edge switches
# Example: MUM-ED-01, MUM-ED-02 (Floor 1)

# Step 2: Disable fabric on affected switches only
# DNAC: Provision > Inventory > [MUM-ED-01] > Actions > Delete from Fabric Site

# Step 3: Restore legacy configuration
configure terminal
 interface range GigabitEthernet1/0/1-48
  switchport mode access
  switchport access vlan 100
  no authentication port-control auto
  no dot1x pae authenticator
  no mab

# Step 4: Verify floor operation
show vlan brief
show interface status

# Other floors continue on fabric

4.11.4 Rollback Configuration Backup

# Pre-cutover backup script (run on all devices)

#!/bin/bash
# backup_configs.sh

DEVICES="MUM-ED-01 MUM-ED-02 MUM-ED-03 ..."
DATE=$(date +%Y%m%d)

for device in $DEVICES; do
  ssh netadmin@$device "show running-config" > backup/${device}_${DATE}.txt
  ssh netadmin@$device "copy running-config flash:pre-cutover-backup.txt"
done

# Verify backups
ls -la backup/