6.1 Migration Strategy

6.1.1 Migration Approach Selection

Approach Description Risk Duration Selected
Big Bang All sites simultaneously High 4 weeks
Phased by Region Region at a time Medium 32 weeks
Phased by Site Site at a time Low 52 weeks
Phased Hybrid Hub sites first, branches parallel Medium-Low 40 weeks SELECTED

Rationale for Phased Hybrid Approach: - Hub sites migrated sequentially (risk management) - Branch sites migrated in parallel within regions (efficiency) - Lessons learned from pilot applied to subsequent sites - Resources optimized across teams

6.1.2 Migration Phases

+------------------------------------------------------------------+
|                    MIGRATION TIMELINE (40 WEEKS)                  |
+------------------------------------------------------------------+

Phase 1: Foundation (Weeks 1-6)
+----------------------------------------------------------------+
| Week 1-2  | Week 3-4  | Week 5-6                               |
| DNAC      | ISE       | Integration                            |
| Install   | Deploy    | DNAC-ISE, Underlay Prep                |
+----------------------------------------------------------------+

Phase 2: Pilot (Weeks 7-10)
+----------------------------------------------------------------+
| Week 7-8            | Week 9-10                                |
| Mumbai Pilot        | Validation & Refinement                  |
| (1 Building)        | Lessons Learned                          |
+----------------------------------------------------------------+

Phase 3: Hub Sites (Weeks 11-22)
+----------------------------------------------------------------+
| Week 11-12 | Week 13-14 | Week 15-16 | Week 17-18 | Week 19-22 |
| Mumbai     | Chennai    | London     | Frankfurt  | NJ + Dallas|
| Full       | Full       | Full       | Full       | Full       |
+----------------------------------------------------------------+

Phase 4: Branch Sites (Weeks 23-34)
+----------------------------------------------------------------+
| Week 23-26        | Week 27-30        | Week 31-34             |
| APAC Branches     | EMEA Branches     | Americas Branches      |
| (5 sites)         | (12 sites)        | (15 sites)             |
+----------------------------------------------------------------+

Phase 5: Optimization (Weeks 35-40)
+----------------------------------------------------------------+
| Week 35-36        | Week 37-38        | Week 39-40             |
| Performance       | Training &        | Documentation &        |
| Tuning            | Knowledge         | Handover               |
|                   | Transfer          |                        |
+----------------------------------------------------------------+

6.1.3 Site Migration Sequence

Order Site Type Devices Endpoints Duration Dependencies
1 Mumbai (Pilot) Hub 10 500 2 weeks DNAC/ISE ready
2 Mumbai (Full) Hub 52 4,200 2 weeks Pilot success
3 Chennai Hub 40 3,100 2 weeks Mumbai complete
4 London Hub 46 3,500 2 weeks Chennai complete
5 Frankfurt Hub 32 2,400 2 weeks London complete
6 New Jersey Hub 56 4,500 2 weeks Frankfurt complete
7 Dallas Hub 36 2,800 2 weeks NJ complete
8-12 APAC Branches Branch 5 each 200-400 4 weeks Hub complete
13-24 EMEA Branches Branch 4 each 150-300 4 weeks Hub complete
25-39 Americas Branches Branch 4 each 150-300 4 weeks Hub complete

6.1.4 Migration Dependencies

+------------------------------------------------------------------+
|                    DEPENDENCY MATRIX                              |
+------------------------------------------------------------------+

DNAC Installation
    |
    +--> ISE Deployment
    |        |
    |        +--> DNAC-ISE Integration
    |                  |
    |                  +--> Policy Definition
    |                           |
    +--> Underlay Provisioning   |
              |                  |
              +--> Fabric Site Creation <--+
                        |
                        +--> Node Provisioning
                                  |
                                  +--> Host Onboarding
                                           |
                                           +--> User Migration
                                                    |
                                                    +--> Legacy Decommission

6.1.5 Resource Requirements

Phase Network Engineers Security Engineers Project Manager Vendor Support
Phase 1 4 2 1 2 (Cisco)
Phase 2 4 2 1 2 (Cisco)
Phase 3 6 3 1 2 (Cisco)
Phase 4 8 2 1 1 (Cisco)
Phase 5 4 2 1 0