4.1 Deployment Strategy Overview

4.1.1 Phased Migration Approach

The migration follows a structured 5-phase approach minimizing business disruption while ensuring systematic validation at each stage.

PHASE 1          PHASE 2          PHASE 3          PHASE 4          PHASE 5
Foundation       Pilot Site       Hub Sites        Branch Sites     Optimization
(Weeks 1-6)      (Weeks 7-10)     (Weeks 11-22)    (Weeks 23-34)    (Weeks 35-40)
    |                |                |                |                |
    v                v                v                v                v
+----------+    +----------+    +----------+    +----------+    +----------+
| DNAC/ISE |    | Mumbai   |    | Chennai  |    | APAC     |    | Tuning   |
| Install  |    | Pilot    |    | London   |    | EMEA     |    | Training |
| Underlay |    | Fabric   |    | Frankfurt|    | Americas |    | Handover |
| Prep     |    | Test     |    | NJ/Dallas|    | Branches |    | Document |
+----------+    +----------+    +----------+    +----------+    +----------+

4.1.2 Deployment Timeline

Phase Duration Sites Activities Exit Criteria
Phase 1: Foundation 6 weeks N/A DNAC cluster, ISE deployment, underlay prep DNAC/ISE operational, underlay validated
Phase 2: Pilot 4 weeks Mumbai (partial) Single building fabric, limited users 500 users migrated, 95% success rate
Phase 3: Hub Sites 12 weeks 6 hub sites Full fabric deployment, all VNs All hub sites operational, 99.9% uptime
Phase 4: Branch Sites 12 weeks 30+ branches Fabric-in-a-Box, SD-WAN integration All branches migrated, failover tested
Phase 5: Optimization 6 weeks All Performance tuning, training, handover SLA compliance, team certified

Total Duration: 40 weeks (10 months)

4.1.3 Governance Structure

                    +---------------------------+
                    |    Steering Committee     |
                    |    (Monthly Review)       |
                    +---------------------------+
                               |
            +------------------+------------------+
            |                                     |
    +---------------+                     +---------------+
    | Project       |                     | Technical     |
    | Management    |                     | Review Board  |
    | (Weekly)      |                     | (Weekly)      |
    +---------------+                     +---------------+
            |                                     |
    +-------+-------+                     +-------+-------+
    |               |                     |               |
+-------+    +----------+           +----------+    +----------+
| Change|    | Resource |           | Network  |    | Security |
| Mgmt  |    | Tracking |           | Team     |    | Team     |
+-------+    +----------+           +----------+    +----------+

4.1.4 Change Control Process

Change Type Approval Required Lead Time Rollback Window
Standard (documented procedure) Team Lead 24 hours 2 hours
Normal (planned change) CAB 5 business days 4 hours
Emergency (critical fix) Emergency CAB 2 hours 1 hour
Major (site cutover) Steering Committee 10 business days 8 hours